The high-level flood risk assessment submitted with the Outline Planning Proposal in 2006 states that
- The development will increase the amount of surface water from the site
- It is proposed that surface water will be collected in balancing ponds and discharged to existing ditches on the east of the site!
- Foul water for the site will be pushed through existing sewers. No review of the existing sewers capacity was carried out at the time.
A map of the existing sewers is shown below:
Foul Water will either drain via gravity to the existing sewers or will be pumped to the south most likely to into node 5101 (see map below for a zoom into the relevant node).
All rights acknowledged.
Related posts:
- Water Drilling – Housing Site Did you know that in April / May a survey team...
- Flooding Risks Woking Borough Council publishes a series of detailed maps that...
- Plea to bring back Moor Lane island As featured in the February 28, 2009 edition of the...
- Access Planning Application Documents For those struggling to find or download the documents here...
- County Highway Authority – Response to Access Application Copied verbatim a reply to Katie Dunk (Woking Borough Council...